SSEE Parintins II
Electricity
Start
january
2021
End
january
2023
Location
Amazon (Brazil)
Client
Amazonas Energía
Scope
Installation of the Parintins Dois substation (138/13.8 kV) and 2 40 MVA transformers, including supply of the main equipment, civil engineering work and engineering.
Features
  • Installation of the Parintins Dois substation (138/13.8 kV)
  • Installation of 2 40 MVA transformers (138/13.8 kV)
  • 10 feeder lines (13.8 kV)
Project developed by: